Purchase Price
£500,000
Build & Fees
£3,200,000
Gross Development Value
£5,300,000
Project Overview:
- Transformation of a brownfield site into a 44+ bed new-build development.
- Multiple units designed for students seeking city-centre living in Derby.
Scope of Work:
- Full site strip, planning, and construction managed by our team.
- Navigated challenges of varying ground levels across the site.
Construction Details:
- Built using a timber frame structure, fully constructed (including steels and internal stud walls) within 10 weeks.
- Features a mansard roof with cladding for a sleek, modern finish.
Additional Features:
- On-site parking with electric car charging points.
- High-end interior fit-out designed by our group to enhance tenant living facilities.
Project Timeline:
- Construction began in December 2023 and completed in January 2025.